City Working Days (CWD)
Effective on 2/12/25
Any projects with an Actual Bid Advertise date on or after 2/12/25 will only have one option for Estimated Working Days within Procurement tab, which is “City Working Days“
City Working Days will use City Holidays within its calculation of the Actual First Chargeable Date and the Original Date of Completion when generating the NTP.
FAQs
Q: What will happen to CPMS Projects with Bid Advertise date before 2/12/25?
A: The existing CPMS projects will continue as planned. Nothing changes. This change is effective for projects with Bid Advertise date of Feb 12, 2025 or later.
Q: What will happen to the Calendar Days option for Estimated Working Days?
A: Calendar Days will only be applicable for projects with Bid Advertise date before 2/12/25. Otherwise, it will no longer be in use or selectable.
Q: Does the City’s furlough days count as a holiday?
A: Yes.
Q: Does Bid Packager have updated Special Provisions document?
A: Yes
Q: Will CPP Schedule Planner Sheet calculate on new rules?
A: Yes, projects provisioned/created after Jan 27,2025 will now calculate end dates based on city working days and will follow City Holiday Calendar.
Q: Will CPP Scheduler Sheet automatically switch to City Working Days for already provisioned projects?
A: No, this is on request basis. Connect with CPMS team to update the scheduler sheet for your project(s).
Change in Procurement Tab
Estimated Working Days will show City Working Days as option for projects with Bid Advertise date of Feb 12, 2025 or later.
Bid Packager is updated with latest documents. Procurement Manual is updated.
Note : No change for older procurement. They stay on Calendar / Working days as selected.
Change in CPP Schedule Planner Sheet
The new City Working Days (CWD) system applies to workspaces provisioned or created after Jan 27, 2025.
Key Updates:
City holidays of year 2025 - 2027 are set in Schedule Planner.
Any start or end dates that fall on a city holiday will be shifted to the next working day.
Durations are now calculated in working days (Monday to Friday, excluding weekends and holidays, i.e. 14 calendar days before is equivalent to 10 working days now, because of excluding the weekends).
Notes in the right column of the sheet have been updated to reflect these changes.
The Start Date cell in the Project Start row is now highlighted in bright yellow as a reminder.
Important Notes (for workspaces created before January 27, 2025):
If your project is in early phases (Ph 1-4) then contact CPMS to re-create / update workspaces in order to acquire this new feature.
Need assistance?
For any questions on City Working Days, Please contact Amanda Lei or Director’s Office.
For any questions on CPMS, CPP & CMS, Please contact CPMS Tech Team.