Procurement Documents Home Page

The documents and process listed here is for CIP Projects only.

Getting Started

The Public Works Procurement Team assists the responsible Project Manager (PM) in the completion and facilitation of the tasks associated with Pre-Advertisement, Advertisement and Post-Advertisement. Contract Award and Execution tasks are completed under the jurisdiction and procedures of the respective project delivery Department/Division.

Familiarize yourself with CPMS Procurement Tab

CPMS Pre-Requisites before creating Procurement.

Important Days for Major Projects

Bid Advertise is always on Wednesdays

Bid Opens on Thursdays at 11:00am

CIP Construction Major Process

Major Public Works Project Contract is defined in Municipal Code Section 27.02.070. Please note there are different versions of Bid Documents for CIP City-wide, RWF & Airport.

Quick Links for Document Center

Project Labor Agreement

CIP Construction Minor Process

Minor Public Works Project Contract as defined in Municipal Code Section, Title 27. Please note there are different versions of Bid Documents for CIP City-wide & Airport.

Quick Links for Document Center

CIP Consultant Process

If looking for Technical Consultant Evaluation with undefined Scope of Service (Master Consultant Agreement) then consider Request for Qualifications (RFQ)

If looking for Technical and Cost Consultant Evaluation For Defined Scope of Service (Standard Consultant Agreement) then consider Request for Proposal (RFP)

See Details here

Quick Links for Document Center

CIP Construction Pre-Qualification

Discuss pre-qualification with Procurement Team if your project’s Engineer’s Estimate is $5,000,000 or more.

See Details here

Contact Us

Procurement Team | PW_Procurement@sanjoseca.gov | 5th Floor | San Jose City Hall