Data Definitions - Main tab
Data Definitions - Main tab
Data Definitions - Schedule tab | Data Definitions - Notes tab
Field or Button Name | Definition | Posted to Web? | Comments/Pending Changes |
---|---|---|---|
Assign Delegates | Enables you to give another user the ability to edit your project. User must have one of these roles: Implementation Manager, Division Manager, Section Manager | ||
cFiles | Enables user to create the project's entry in cFiles, a separate system on the public web site which provides access to record drawings. | ||
Construction Contract Amount | This amount should show the best available estimate of the construction contract amount. The amount should be filled in initially by the Project Manager when a Preliminary Estimate has been prepared for the project. Preliminary estimates are normally completed during Phase 1 of a project. Prior to bid opening, this field should be updated whenever an updated construction estimate is prepared. After bid opening, the project manager should enter the actual construction award amount in this field. | N | |
Cost Estimates | Enables user to open up the project's cost estimates. Project must have at least one estimate created already. | ||
Total Project Cost | The contract amount plus contingencies and/or soft costs | N | formerly titled "Contract Award Memo Total" |
Council Dist | Use the Council District number or numbers that the project is located within. All projects at the Airport should use the City-Wide designation. | Y | |
City Service Area | City Service Areas integrate Core Services provided by individual departments into the City’s key lines of business, as viewed from the community’s perspective. A collection of Core Services from various partner departments, CSAs enable us to plan and show results of the collaboration among the departments at a higher organizational level. | Y | |
Description | Provide general information that defines the project and its purpose. Initially this should be the same as what is described in the budget document. | Y | |
Division | Lead Implementing Department Division for the project. | Y | |
Fiscal Year | The initial fiscal year for which activity begins on the project or in which it is anticipated to begin. Typically this is the first year that funding appears in the CIP. | N | |
Funding Status |
| N | |
Implementation Manager | Primary manager responsible from the implementing department. May change from design to construction phase. | Y | |
Location | Use cross streets, address number or well known building/place/geographic feature names to help pinpoint locations. Try to spell out acronyms in project locations. Try to identify the reach of the project (i.e. Asbury Street between Guadalupe and First Street.) Supplements GIS map & IPC map. | Y | |
Owner Department | The department with the overall responsibility for taking a project from conception to completion. Typically this is the department responsible for project budgeting and scoping. May be the same as the implementing department under certain circumstances | N | |
Program | The PRIMARY CIP funding source for the project. If more than one source exists, the largest contributing source should be selected. For SNI Priority projects, the SNI Area is selected here regardless of the funding source. | N | |
Open Push Report | A report showing all projects that meet criteria for posting to the public site. | ||
Owner Mgr | Responsible manager from the owner department | N | |
Project Classification | Used to determine type of project. I.e., Construction vs Non-Construction and/or City Managed vs Outside Agency Managed. See detailed definition sheet for further information | N | |
Project Phase | Only required for projects showing "scheduled" status in "Schedule Status" field. At this time, only one phase may be selected at a time. If more than one phase is active at any one time, Manager should select the furthest phase reached in the project timeline. For example, if the project is under construction but additional design work is occuring, Manager should select "Phase V - Construction" | Y | |
Push to Public | Enables Division Manager and Section Manager the ability to push the project's data to the public site. For Implementation Managers, a blue color indicates the project meets criteria for posting to the web and so it should be reviewed. If the button is white, clicking on the button will show why the project doesn't meet the criteria for posting to the public site. | ||
Schedule Status | Either "Scheduled" or "Schedule Pending" must be selected. If schedule pending is selected, manager should provide comment in notes field to explain timeline for completing schedule. For "Funded" projects only (Classifications of "Construction - Programs, and Ops and Services" do not need to utilize this field). | N | |
Section | Lead Implementing Department Section for the project. | N | |
Section Manager | Name of DPW section manager in charge of the project. | N | |
, multiple selections available,
Related content
1 - Main tab
1 - Main tab
Read with this
Program Field Mapping
Program Field Mapping
More like this
CIP Construction Pre-Qualification Manual
CIP Construction Pre-Qualification Manual
More like this
Procurement Documents Home Page
Procurement Documents Home Page
More like this
CIP Minor Construction Project Procurement Manual
CIP Minor Construction Project Procurement Manual
More like this
CIP Project Classification
CIP Project Classification
Read with this