When the Engineer’s Estimate is entered/updated in the Project Input - Procurement tab, the Award Authority is automatically assigned in the database according to these rules:
- Construction Contracts, including Design Builds, Minor PW Construction Contracts and Service and Maintenance:
- If the Engineer’s Estimate is less than $1M, then the Award Authority is set to Director.
- Otherwise, it is assumed the Engineer’s Estimate is $1M or greater, and the Award Authority is set to City Council.
- Consultant Agreements, and all the other agreements we have set up that aren’t above:
- If the Engineer’s Estimate is less than $250K, then the Award Authority is set to City Manager.
- Otherwise, it is assumed the Engineer’s Estimate is $250K or greater, and the Award Authority is set to City Council.
This is where the Engineer’s Estimate is entered:
This is where the Award Authority is displayed:
** Consultant Agreements, and all the other agreements that are treated like Consultant Agreements:
- Consultant Agreement
- First Amendment
- Second Amendment
- Third Amendment
- Fourth Amendment
- Fifth Amendment
- Master
- Consent of Assignment
- Continuation
- Joint Agency
- Shelter
- Standard
- Other
, multiple selections available,
Related content
Project Labor Agreement
Project Labor Agreement
More like this
Document Center - Consultant
Document Center - Consultant
More like this
CIP Consultant Procurement Manual
CIP Consultant Procurement Manual
More like this
Procurement Documents Home Page
Procurement Documents Home Page
More like this
CIP Minor Construction Project Procurement Manual
CIP Minor Construction Project Procurement Manual
More like this
Document Center - Major Construction
Document Center - Major Construction
More like this