Project Updates:
April 28, 2021
FOURTH ST CLOSURES for 84-inch pipe installation, temporary sewer bypass, utilities connections, and dewatering well construction:
Fourth St from Gish Rd intersection through Rosemary St intersection is scheduled to re-open in mid-May.
Fourth St will be closed from the south side of the Rosemary St intersection through the Commercial St Intersection intersection through Fall 2021.
WHAT TO EXPECT
Southbound lane closure. Northbound lane will remain open.
Traffic control will be in place.
Intermittent intersection closures.
At least one driveway access will be maintained for each property.
Detours will be in place to route drivers around the area of work.
No Parking signs will be posted and parking will be restricted.
Temporary sewer service interruptions, which will be coordinated with affected services ahead of time.
General Project Information:
The Fourth St Sewer project will improve the capacity of the City's sewage system by replacing 48-inch and 54-inch diameter sanitary sewer pipes with 4,500 feet of 84-inch diameter pipes along North street and approximately 300 feet of 72-inch diameter pipes along Commercial Street.
Fourth St is a busy San Jose roadway, with fronting residences and businesses, which will require extensive community outreach and complex traffic management. The project will cross under US 101, I-880, several large storm pipes and existing utilities, requiring permits to perform work within Caltrans' right of way.
The project will allow:
future shutdown and maintenance of City sewage systems
future decommissioning of deteriorated 60-inch brick sewer that runs parallel to Fourth Street, which was built in the 1890's
sewage flow from Commercial St to Old Bayshore Rd north of US 101
installation of a small diameter local collector sanitary sewer system
Project Map:
Schedule:
Milestones | Duration |
---|---|
Construction Begins | Summer 2019 |
Tunneling Work (Under US 101) | Complete |
Fourth St Pipe Replacement | Fall 2019 – Summer 2021 |
Pipe Laying Work (Under I-880) | Fall 2020 – Spring 2021 |
Commercial St Pipe Replacement | Winter 2021 – Fall 2021 |
Repaving | Spring 2021 – Fall 2021 |
Project Completion | Fall 2021 |
Construction Hours:
Construction will take place Monday through Friday, 7:00am to 5:30pm. No work is anticipated on weekends, unless warranted. All construction dates and times are subject to change due to weather and unforeseen conditions.
Anticipated Project Impacts:
Shutdown of 1/4 City interceptors for maintenance/repair
Traffic will be temporarily impacted during construction along North Fourth Street
Construction Notice Archive:
Construction Update - August 2020
View file | ||
---|---|---|
|
Construction Update - May 2020
View file | ||
---|---|---|
|
Construction Update - November 25, 2019
View file | ||
---|---|---|
|
Construction Update - November 8, 2019
View file | ||
---|---|---|
|
Contact Information:
Project Email:
Project Info Line:
(888) 778-8453
24hr Emergency Line:
(408) 767-6362
Project Fact Sheet:
View file | ||
---|---|---|
|
COVID-19 INFORMATION Fourth St Sewer construction activities will continue as planned due to an exemption for public works construction in the Santa Clara County Health Officer shelter-in-place order. The City of San Jose has evaluated all existing construction projects and has designated the Fourth Street project as an Essential Governmental Function authorized to continue construction pursuant to Section 13.f.v.4 of the March 31, 2020 Health Officer order. For more information about ongoing projects, please visit the Capital Project Management System website. |
---|